Substation Scout

Patriot

In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission, in Pima County.

Pimacounty
138kV as printed
TEPutility plan
Phase 1: 12/11/2023; Phase 2: 07/18/2024in service, as printed

Described as new. The quoted wording calls this substation proposed or future. “Planned Patriot 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.46

Note. The plan says phase 1 (Irvington Substation to Patriot Substation) was completed 12/11/2023 and phase 2 (Patriot Substation to East Loop Substation) 07/18/2024, but still labels Patriot "Planned".

Also mentioned: “To connect the planned Patriot 138/13.8-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.46

County: “with an interconnection at the Port Substation (Section 18, Township 15 South, Range 15 East) and the Patriot Substation (Section 31, Township 14 South, Range 15 East), and terminating at the East Loop Substation (Section 08, Township 14 South, Range 15 East, each located within Pima County, Arizona.” — ACC eDocket, Line Siting docket L-00000C-20-0007-00186, docket description, retrieved 2026-11-20.

Location

32.1763, -110.8437 · Pima County, AZ · view on a map

OpenStreetMap, corroborated. An OpenStreetMap feature carries this exact name, and a cited source agrees. Accurate to about ±150 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: OpenStreetMap way 1202440463, name "Patriot Substation", power=substation, voltage 138000 (mapped as construction 2023-08, as a substation since 2024-02); point is the centroid of the mapped yard (about 320 x 150 m). Corroborated by TEP's CEC application: "The planned Patriot 138 kV Substation will be located on land owned by the COT, on the southwest corner of Escalante Road and Kolb Road"; the mapped yard sits at the southwest corner of Escalante Road (32.1774) and Kolb Road (-110.8410). Accuracy ±150 m covers the yard footprint.

Note: Probably already built: the plan itself says Phase 1 (Irvington to Patriot Substation) was completed 12/11/2023 and Phase 2 (Patriot to East Loop) 07/18/2024, yet still labels Patriot "Planned"; OSM has mapped the yard as a 138 kV substation since 2024-02. The CEC application (2020) said it was "scheduled to be in service by the end of 2022".

Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.46 · ACC eDocket, Line Siting docket L-00000C-20-0007-00186 (Case No. 186): Irvington to East Loop 138 kV Transmission Line Project (n/a (retrieved 2026-11-20)), docket description · TEP CEC Application, Irvington to East Loop 138 kV Transmission Line Project (Case No. 186) (January 2020 (filed 2020-01-15)), PDF p.23 · OpenStreetMap: way 1202440463 "Patriot Substation" and Kolb / Escalante roads (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

The project in the plan

ProjectWhere in the planLine siting case
Irvington 138-kV Substation - East Loop 138-kV Substation Transmission Line with loop-in at the Planned Patriot 138-kV Substation and Planned Port 138-kV Substationp.46Case No. 186

Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.