Substation Scout

Cochise

In the Arizona Electric Power Cooperative ten-year transmission plan filed with the Arizona Corporation Commission.

—county (not printed)
230kV as printed
AEPCOutility plan
January 2026in service, as printed

Described as new. The quoted wording calls this substation new. “Cochise 230 kV Substation : New 230 kV substation to accommodate renewable generation in the vicinity of the AEPCO' s Apache Generating Station. (January 2026)” — Arizona G&T Cooperatives 2026-2035 Ten Year Plan, p.8

Note. Probably built. The plan dates it January 2026, and AEPCO's 2026 WECC progress report says the Apache Solar 2 project is "interconnected to AEPCO's new 230 kV Cochise Substation", in service since December 2025.

Also mentioned: “Cochise 230 kV Substation: New 230 kV substation to accommodate renewable generation in the vicinity of the AEPCO' s Apache Generating Station. (January 2026)” — Arizona G&T Cooperatives 2026-2035 Ten Year Plan, p.41 · “2026 - Cochise 230 kV Substation” — Arizona G&T Cooperatives 2026-2035 Ten Year Plan, p.38

Note. Purpose as printed: "to accommodate renewable generation in the vicinity of the AEPCO' s Apache Generating Station".

No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.

Location

Cochise County, AZ

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: No point. The Special Use site plan draws an "AEPCO Substation" beside the project's "Substation & BESS Area" but is labelled "Panel layout, AEPCO Substation, Substation & BESS Area are subject to change", and was not georeferenced. OSM has two unnamed adjoining substations at 32.0722-32.0733 N, 109.9218-109.9241 W inside the OSM "Roadrunner Solar and BESS" polygon (start_date 2025-12); unnamed, so not used for a point.

Sources: Arizona G&T Cooperatives 2026-2035 Ten Year Transmission Plan (Arizona Electric Power Cooperative, Inc.), ACC Docket E-99999A-25-0006 (filed 2026-01-30), p.8 · Arizona Electric Power Cooperative 2026 Annual Progress Report to WECC (Apache Solar 2 (Road Runner) Solar and Battery Energy Storage Facility) (2026), p.1 · Cochise County Planning & Zoning Commission, Special Use application by AEPCO for Apache Solar II (Roadrunner), with conceptual site plan (PZC agenda 2023-12-13), application pp.1-4; site plan p.10 · OpenStreetMap: power features near Apache Generating Station (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

The project in the plan

ProjectWhere in the planLine siting case
Cochise 230 kV Substationp.8Not printed

Generation interconnection requests filed in Cochise, AZ: APS queue, 0 active of 10. Same county, not the same substation.

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.