Vine

In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission, in Pima County.

Pimacounty
138kV as printed
TEPutility plan
2027in service, as printed

Described as new. The quoted wording calls this substation proposed or future. “Planned Vine Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.49

Also mentioned: “To loop-in planned Vine Substation into the TEP transmission” — TEP 2026-2035 Ten-Year Transmission Plan, p.49 · “Planned Vine 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.74

County: “with an interconnection at the planned Vine substation (section 06, township 14 south, range 14 east), and terminating at the existing Kino substation (section 30, township 14 south, range 14 east), each located within the city of Tucson, Pima County, Arizona.” — ACC eDocket, Line Siting docket L-00000C-24-0118-00232, docket description, retrieved 2026-11-20.

Location

32.2426, -110.9494 · Pima County, AZ · view on a map

Parcel or address in a filing. A filing names the parcel or address; the point is its center. Accurate to about ±75 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Parcel printed by TEP: its August 2025 Vine Substation open-house boards list the selected site as parcel 12310001K ("Parcel selected for purchase (1.596 ac. selected out of the parcel)"). Pima County's parcel layer now carries 12310001K as a 1.596-acre parcel owned by Tucson Electric Power Co; the point is that parcel's centroid (Pima County GIS). TEP's construction-update map outlines the same "Vine Substation Parcel" on the east side of N Vine Ave between E Chauncey Ln and E Lee St. Accuracy ±75 m covers the parcel.

Note: Timing: TEP's project page says "The substation is expected to be in service by 2029"; the plan says in service 2027. The City of Tucson Zoning Examiner approved the Special Exception Land Use Permit in February 2026 and Mayor and Council denied an appeal on June 9, 2026.

Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.49 · ACC eDocket, Line Siting docket L-00000C-24-0118-00232 (Case No. 232): Midtown Reliability Project (n/a (retrieved 2026-11-20)), docket description · TEP, Vine Substation Neighborhood Meeting Boards (site selection results table) (August 2025), p.3 · TEP, Vine Substation construction update map (Vine Substation Parcel) (n/a (retrieved 2026-11-20)), p.1 · Pima County GIS, Parcel Centroids (parcel 12310001K) (n/a (retrieved 2026-11-20)), layer 0 · TEP, Vine Substation project page (n/a (retrieved 2026-11-20)), Required Approvals and Timeline. Researched by Substation Scout; checked November 21, 2026.

The project in the plan

ProjectWhere in the planLine siting case
Kino 138-kV Substation - DeMoss Petrie (DMP) 138-kV Substation with loop-in at planned Vine 138-kV Substationp.49Case No. 232

Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.