Sidewinder
In the Salt River Project ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation new. “New SY-33 230 kV Switchyard (named Sidewinder)” — SRP 2026-2035 Ten Year Plan, p.27
Note. The plan gives the switchyard's estimated in-service date as 2023; it does not say whether it has been placed in service.
Also mentioned: “to a new 230 kV switchyard (SY-33) located near the northwest corner of Elliot Road and Sossaman Road in the City of Mesa” — SRP 2026-2035 Ten Year Plan, p.27
Note. The plan prints the switchyard under its earlier label SY-33: "New SY-33 230 kV Switchyard (named Sidewinder)".
Note. Purpose as printed: "This is a single customer requested project and is not triggered by system load growth." The switchyard feeds two customer-owned 230/13.8 kV substations, Diamondback (constructed) and Nexus (under construction).
Note. The CEC docket for Project Red Hawk (L-00000B-19-0219-00184) describes "a switchyard ... all within the City of Mesa, Arizona in Maricopa County" but does not print the Sidewinder or SY-33 name, so no county is given.
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
33.3565, -111.6784 · Maricopa County, AZ · view on a map
Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±100 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Symbol anchored: the drawn rectangle (orange fill, green outline) labelled "Approximate Location of Switchyard" on the CEC's Exhibit A aerial (map rotated, north to the left). Scanned at 150 dpi; latitude from East Elliot Road (33.35044 at Sossaman) and the Browning - Santan 230 kV corridor (OSM 33.358), giving 1.70 m/px; longitude from South Sossaman Road (-111.67064) at the same square-pixel scale of the orthophoto. Point is the centre of the drawn rectangle. The CEC says the switchyard "shall be located in the area depicted in Exhibit A and shall be located as far south as practicable within the designated area". ±100 m (the drawn area and the read).
Sources: SRP 2026-2035 Ten-Year Transmission Plan (Salt River Project Agricultural Improvement and Power District), ACC Docket E-99999A-25-0006 (A.R.S. 40-360.02 ten-year plans) (filed 2026-01-29), p.27 · ACC Line Siting Case No. 184 (Docket L-00000B-19-0219-00184), Certificate of Environmental Compatibility, Project Red Hawk, with Exhibit A aerial (docketed 2019-11-18 (Commission Decision No. 77511…), Project Description pp.2-3; Exhibit A p.12; Exhibit B parcel descriptions · BLM PLSS CadNSDI section polygons (Sec 7, T1S, R7E, Gila and Salt River Meridian), counties intersecting each section from Census TIGERweb State_County (n/a (queried 2026-11-20)), layer 2 · OpenStreetMap: Elliot Rd, Sossaman Rd, Browning - Santan 230 kV lines, substations near the site (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Red Hawk 230 kV (2023-TBD) | p.27 | Decision No. 77511 |
Generation interconnection requests filed in Maricopa, AZ: APS queue, 82 active of 259. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.