Lago del Oro
In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission.
Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. “Planned Lago del Oro 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.62
Existing station: An existing 46 kV substation named Lago Del Oro; the plan's "Planned Lago del Oro 138-kV Substation" adds 138 kV there. Source: OpenStreetMap way 670478956 (power=substation, voltage 46000).
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
32.4988, -110.8923 · view on a map
OpenStreetMap, corroborated. An OpenStreetMap feature carries this exact name, and a cited source agrees. Accurate to about ±150 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: The existing yard: OpenStreetMap way 670478956, "Lago Del Oro Substation" (power=substation, voltage 46000); the point is the centre of the mapped outline. The plan adds 138 kV at this existing TEP station (an expansion, not a new site), so the existing yard is where the work is planned.
Note: Reclassified as an expansion (2026-11-21): the plan's 138 kV "Lago del Oro" substation is at the existing 46 kV Lago Del Oro Substation.
Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.62 · OpenStreetMap: Lago del Oro Parkway and existing "Lago Del Oro Substation" way 670478956 (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Planned Lago del Oro 138-kV Substation - Rancho Vistoso 138-kV Substation | p.62 | Not printed |
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.