Franco Wash
In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission, in Pima County.
Described as new. The quoted wording calls this substation proposed or future. “Planned Franco Wash 138-kV Switchyard” — TEP 2026-2035 Ten-Year Transmission Plan, p.47
Also mentioned: “S Country Club Rd. The planned Franco Wash Switchyard” — TEP 2026-2035 Ten-Year Transmission Plan, p.47
Note. The plan says the project is "in response to a request to serve a customer load".
Note. The OCR text layer misreads the dates as 2826/2827; the page image prints construction start 2026 and in service 2027.
County: “loop into the proposed Franco Wash switchyard (Section 31, Township 15 South, Range 14 East). The proposed transmission line and switchyard would be located within the city of Tucson and Pima County.” — ACC eDocket, Line Siting docket L-00000C-23-0284-00227, docket description, retrieved 2026-11-20.
Location
32.0774, -110.9459 · Pima County, AZ · view on a map
Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±250 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Symbol anchored: the yellow triangle "Proposed Franco Wash Switchyard" on Exhibit C-1 (1:30,000) of TEP's CEC application. Georeferenced on S Nogales Highway (-110.9587), the Section 31/32 line (-110.9435, BLM PLSS) and the 138 kV line turning south near S Country Club Road (-110.9268), about 3.5 m per pixel at 200 dpi; the triangle sits 65 px west of the section line and 53 px north of E Old Vail Connection Road (32.0757). The point falls in Section 31 T15S R14E as printed. Accuracy ±250 m.
Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.47 · ACC eDocket, Line Siting docket L-00000C-23-0284-00227 (Case No. 227): Aerospace Research Campus Transmission Project (n/a (retrieved 2026-11-20)), docket description · TEP CEC Application, Aerospace Research Campus Transmission Project (Case No. 227) (October 2023 (filed 2023-10-20)), PDF p.16 · BLM PLSS CadNSDI, section polygons (with Census TIGERweb county polygons) (n/a (retrieved 2026-11-20)), layer 2 · OpenStreetMap: S Nogales Highway, E Old Vail Connection Road, S Country Club Road, TEP 138 kV line (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Aerospace Research Campus Transmission Project | p.47 | Case No. 227 |
Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.