Substation Scout

Tailings

In the Salt River Project ten-year transmission plan filed with the Arizona Corporation Commission.

—county (not printed)
115kV as printed
SRPutility plan
TBDin service, as printed

Described as new. The quoted wording calls this substation new. “New 115 kV Switchyard at Customer's Tailings Storage Facility (TSF), tentatively named "Tailings Switchyard"” — SRP 2026-2035 Ten Year Plan, p.30

Also mentioned: “SRP's 115 kV Tailings Switchyard located at the TSF.” — SRP 2026-2035 Ten Year Plan, p.30

Note. The plan says the name is tentative and the location is not determined.

Note. The plan says the project "was formerly known as Silver King - New Oak Flat - New Superior 230 kv" and is now split into 115 kV and 230 kV projects.

Note. Purpose as printed: "This is a single customer requested and driven project and is not triggered by system load growth." SRP does not yet hold a CEC for it.

No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.

The project in the plan

ProjectWhere in the planLine siting case
Silver King - Tailings - Oak Flat 115 kV (TBD)p.30Not printed

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first