Independence
In the Arizona Public Service ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation proposed or future. “A new 230kV line will be extended east from the future Independence substation” — APS 2026-2035 Ten Year Transmission Plan, p.42
Also mentioned: “the Jojoba-Rudd line will head generally east to the future Independence substation, targeted in an area south and east of the existing Freedom substation.” — APS 2026-2035 Ten Year Transmission Plan, p.44 · “The future Independence and Hodgkin substations will not be in service in 2030 but are projected to be completed prior to 2035” — APS 2026-2035 Ten Year Transmission Plan, p.75 · “The Independence S00/230kV substation and 230kV lines will relieve loading constraints on the Rudd substation” — APS 2026-2035 Ten Year Transmission Plan, p.41 · “The TS21 substation is now named Independence.” — APS 2026-2035 Ten Year Transmission Plan, p.15
Note. Formerly listed as TS21 (plan p.15).
Note. The project sheets print "(in-service 2030)"; the RMR study (p.75) says it will not be in service in 2030 and Table 2 (p.10) lists its 500/230kV transformers for 2031.
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
Maricopa County, AZ
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. APS's Cotton map draws a green Future Substation triangle labelled "TS21 - 500kV (Potential Site)", read at about 33.3873, -112.4644 on an affine fit to the Freedom, Jojoba and Rudd symbols (1:225,000; check residuals 250-550 m). A potential site on a conceptual map with that residual is a lead, not a point.
Sources: APS 2026-2035 Ten Year Transmission Plan (Arizona Public Service Company), ACC Docket E-99999A-25-0006 (A.R.S. 40-360.02 ten-year plans) (filed 2026-01-30), p.44 · APS Cotton Transmission Corridor Siting Project, open house boards (Conceptual Connections map, SWCA, 1:225,000) (March 2025 (map modified 3/18/2025)), PDF p.4 · APS, Cotton Transmission Corridor 500kV/230kV project page (n/a (retrieved 2026-11-20)), project description. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Independence to Broadway 230kV Line | p.42 | Not printed |
Generation interconnection requests filed in Maricopa, AZ: APS queue, 82 active of 259. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.