Tucson Estates

In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission.

—county (not printed)
138kV as printed
TEPutility plan
2029in service, as printed

Described as new. The quoted wording calls this substation proposed or future. “Planned Tucson Estates 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.58

Also mentioned: “Planned Tucson Estates 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.60

Note. The plan's project title says Tucson Estates was formerly called Bopp-Donald.

Note. The Planned Tucson Estates to South 138-kV line (p.60) is in service 2030.

No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.

Location

32.1641, -111.0910 · Pima County, AZ · view on a map

Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±150 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Symbol anchored: the black dashed "Substation Footprint" outline inside the red "15 Acre Lease Site" on TEP's Tucson Estates PSP Location map. Georeferenced on S Spencer Ave (-111.0889) and S Camino Verde (-111.1056) for scale (about 2.4 m per displayed pixel, consistent with the map's 2,000 ft bar) and W Irvington Rd (32.1625): the footprint centre is ~195 m west of the Spencer Ave line and ~180 m north of Irvington Rd, between Irvington Rd and W Ajo Hwy. The Case 269 CEC Exhibit A triangle "Proposed Tucson Estates Substation" reads at the same place (~60 m away). Accuracy ±150 m.

Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.58 · Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.60 · ACC eDocket, Line Siting docket L-00000C-26-0407-00269 (Case No. 269): Southwest Tucson Reliability Project (n/a (retrieved 2026-11-20)), docket description · Line-Siting Certificate of Environmental Compatibility, Case No. 269 (Southwest Tucson Reliability Project), with Exhibit A map (docketed 2026-11-16), pp.2-4; p.16 · TEP, Tucson Estates PSP Location map (15 Acre Lease Site, Substation Footprint) (n/a (retrieved 2026-11-20)), map · TEP, Tucson Estates Substation project page (n/a (retrieved 2026-11-20)), Project Description · OpenStreetMap: S Spencer Ave, S Camino Verde, W Irvington Rd (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

The project in the plan

ProjectWhere in the planLine siting case
Midvale to Planned Tucson Estates (formerly Bopp-Donald) 138-kV Transmission Linep.58Not printed

Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first