Rio Rico
In the UNS Electric ten-year transmission plan filed with the Arizona Corporation Commission, in Santa Cruz County.
Described as new. The quoted wording calls this substation proposed or future. “Planned Rio Rico 138-kV Switchyard” — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.24
Also mentioned: “Planned Rio Rico Switchyard” — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.23 · “Planned Rio Rico Switchyard” — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.31
Note. The plan says the loop-in is "required to connect into the planned Hermosa mine".
Note. Rio Rico 138-kV capacitor bank additions (p.31) are planned for 2027.
County: “Originating at the Planned Rio Rico Switchyard (Section 12, Township 23 S, Range 13 E) and Terminating at the Planned Harshaw Substation (Section 32, Township 22 S, Range 16 E), Each Located within Santa Cruz County, Arizona.” — ACC eDocket, Line Siting docket L-00000F-23-0060-00218, docket description, retrieved 2026-11-20.
Location
31.4413, -110.9620 · Santa Cruz County, AZ · view on a map
Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±300 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Symbol anchored: the yellow triangle labelled "Proposed Rio Rico Switchyard" (legend: "Proposed Rio Rico Switchyard") on the CEC's Exhibit A map (map rotated, north to the left; scan at 150 dpi). Scale from the map's own scale bar (1 mile = 128 px at 200 dpi, 16.76 m/px at 150 dpi), confirmed by the two range lines drawn 1,140 px (12 miles) apart. Anchors: the R13E/R14E range line drawn just east of the symbol (east edge of Section 12, T23S R13E = -110.9596, BLM PLSS) for longitude; the T22S/T23S township line in R13E (31.4641, BLM; the line jogs ~790 m at the range line, which the map shows) for latitude. Check: the Nogales International Wastewater Treatment Plant ponds drawn north of the symbol fall at 31.451 vs OSM 31.452-31.455. Point lies in Section 12 as printed and ~330 m south of the treatment plant, as the plan says. ±300 m (1:99,000 effective scale, symbol size).
Sources: UNS Electric 2026-2035 Ten-Year Transmission Plan (UNS Electric, Inc.; includes the Nogales Transmission, LLC section), ACC Docket E-99999A-25-0006 (filed 2026-01-30), p.24 · ACC Line Siting Case No. 218 (Docket L-00000F-23-0060-00218), Certificate of Environmental Compatibility, Rio Rico to Harshaw 138 kV Transmission Line Project, Exhibit A (Preferred and Alternative Routes) and Exhibit B (Approved CEC Corridor) (docketed 2023-04-25 (Commission Decision No. 79005…), caption p.1; Exhibit A p.15; Exhibit B p.16 · ACC eDocket, Docket L-00000F-23-0060-00218 description (filed 2023-03-03), docket description · BLM PLSS CadNSDI section polygons (Sec 12 and Sec 1, T23S, R13E; Sec 36, T22S, R13E; T23S R14E), counties intersecting each section from Census TIGERweb State_County (n/a (queried 2026-11-20)), layer 2 · OpenStreetMap: Nogales International Wastewater Treatment Plant, I-19, Ruby Road, Potrero Creek, Sonoita Substation (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Loop-in of Planned Kipper - Valencia 138-kV Transmission Line into Planned Rio Rico 138-kV Switchyard | p.24 | Not printed |
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.