Copper World
In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation proposed or future. “Planned Copper World Switchyard” — TEP 2026-2035 Ten-Year Transmission Plan, p.53
Note. The plan says the line is "to provide electrical service to a proposed large retail customer (mine load) located east of Green Valley, AZ".
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
Pima County, AZ
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. The plan routes the line from Santa Rita "over Lopez Pass to the Copper World substation" but prints no location for the switchyard; TEP's 2023 motion says "the line may now terminate prior to entering the Coronado National Forest", so the 2011 terminus (Rosemont Substation, Sec 30 T18S R16E) is not taken as this switchyard. Not in OSM or HIFLD by name.
Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.53 · ACC eDocket, Line Siting docket L-00000C-11-0400-00164 (Case No. 164): TEP 138 kV line from the proposed Toro switchyard to the Rosemont substation (n/a (retrieved 2026-11-20)), docket description · TEP Motion to Amend Decision No. 73232 under A.R.S. 40-252 (Case No. 164) (filed 2023-03-17), pp.2-3 · TEP CEC Compliance Certification Letter, Decision No. 73232 (Case No. 164) (filed 2026-02-27), condition 19 and 23 status. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Planned Santa Rita Substation to Planned Copper World Switchyard Radial 138-kV Transmission Line | p.53 | Case No. 164 |
Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.