APS interconnection queue

Generator interconnection requests to Arizona Public Service’s transmission system in Arizona (a few rows are in New Mexico and California), as of the end of 2025. APS is not in an RTO.

Annual snapshot: requests through December 31, 2025. From Queued Up: 2026 Edition, the interconnection queue data file of Lawrence Berkeley National Laboratory and GridTracker (Interconnection.fyi), published 2026-05, licensed CC BY 4.0, retrieved 2026-11-21. Not refreshed weekly and not part of Queue Wire’s change log; the live queue has moved since. Confirm any request against the transmission provider’s own queue.

619requests in the snapshot
193active (non-terminal)
59,923active MW
4states covered

Browse & filter all 619 projects →

Planned substations in this footprint: the Substation Expansion Tracker, Arizona section, new and expanded substations named in Arizona planning records.

By resource category

Categories are normalized for filtering only. The raw data-file value is shown on every project page — APS publishes 8 display groups from many more raw strings.

Data quality

No state reported0
No county reported3
No voltage reported71
0 MW (net change / energy-only)0
Terminal status (hidden by default)426

Top counties by active capacity

Top substations by active capacity

SubstationActive projectsActive MW
Four Corners33,500
Delaney52,450
Cholla72,408
Sun Valley52,250
Navajo Substation12,000
Westwing Substation51,775
Cholla Substation41,475
North Gila21,300
Hoodoo Wash41,260
Moenkopi Substation21,250
Panda Substation21,200
Cedar Mountain - Moenkopi Line21,161
APS Chevelon Substation2999
Sitgreaves substation2840
Trilby Wash3750
Hoodoo Wash Substation3750
Moenkopi - El Dorado line1700
Santa Rosa3650
Milligan Substation4630
Delaney SY2600
Tat Momoli- Saguaro Line2593
Delaney Substation1500
Orchard2500
Redhawk Substation1400
Redhawk Switchyard2393

All 95 substation pages, by state → Pages are generated for substations with two or more projects and a recognizable name; interface tie-points and filing-note text are excluded, but those projects still appear in browse and on their county pages.