East Plant
In the Salt River Project ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation new. “New 230 kV Switchyard near the existing Oak Flat 115 kV Substation, tentatively named "East Plant Switchyard"” — SRP 2026-2035 Ten Year Plan, p.29
Also mentioned: “The line starts at the Silver King Receiving Station, runs southwest into the East Plant 230 kV Switchyard” — SRP 2026-2035 Ten Year Plan, p.29
Note. The plan says the name is tentative and the location is not determined ("Near SEC32, T1S, R13E (exact location not determined)").
Note. Purpose as printed: "This is a single customer requested and driven project and is not triggered by system load growth." SRP does not yet hold a CEC for it.
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
Pinal County, AZ
County of the area the plan places it in. No source prints a location. The plan places the substation relative to a mapped feature, and everywhere within that range is in one county. No point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. The plan says the site is "still being determined"; no CEC exists ("SRP does not yet hold a CEC for this project"). Not in OSM or HIFLD by name.
County: the plan prints “Near SEC32, T1S, R13E (exact location not determined)”. That section and all eight sections around it lie wholly in Pinal County (BLM PLSS; Census TIGERweb).
Sources: SRP 2026-2035 Ten-Year Transmission Plan (Salt River Project Agricultural Improvement and Power District), ACC Docket E-99999A-25-0006 (A.R.S. 40-360.02 ten-year plans) (filed 2026-01-29), p.29 · BLM PLSS CadNSDI section polygons (Sec 32, T1S, R13E and its eight neighbours), counties intersecting each section from Census TIGERweb State_County (n/a (queried 2026-11-20)), layer 2. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Silver King - East Plant - West Plant 230 kV (TBD) | p.29 | Not printed |
Generation interconnection requests filed in Pinal, AZ: APS queue, 27 active of 80. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.