Substation Scout

Grier

In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission.

—county (not printed)
138kV as printed
TEPutility plan
2028in service, as printed

Described as new. The quoted wording calls this substation proposed or future. “Planned Grier 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.54

Also mentioned: “Required to connect the planned Grier 138/13.8-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.54 · “Planned Grier 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.55 · “Planned Grier 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.56

No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.

Location

32.4550, -111.2609 · Pima County, AZ · view on a map

Parcel or address in a filing. A filing names the parcel or address; the point is its center. Accurate to about ±250 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Parcel printed by TEP: its Town of Marana rezoning application names Pima County Assessor Parcel No. 217-23-0310 (19.5 acres, 13860 W. Grier Road, E1/2 SE1/4 SW1/4 Sec 19 T11S R11E) as the substation site. The point is that parcel's centroid in Pima County's parcel layer (owner Tucson Electric Power Co, 19.44 GIS acres). The Case 246 CEC Exhibit A triangle "Planned Grier Substation" falls in the same parcel (~140 m from the centroid). Accuracy ±250 m covers the 20-acre parcel (about 200 x 400 m).

Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.54 · TEP, Grier Substation Rezone and Minor General Plan Amendment application to the Town of Marana (submitted 2024-02-22), PDF p.14 · Pima County GIS, Parcel Centroids (parcel 217230310) (n/a (retrieved 2026-11-20)), layer 0 · ACC eDocket, Line Siting docket L-00000C-25-0094-00246 (Case No. 246): Northwest Marana Reliability Project (n/a (retrieved 2026-11-20)), docket description · TEP CEC Application, Northwest Marana Reliability Project (Case No. 246) (filed 2025-05-02), PDF p.21 · Line-Siting Certificate of Environmental Compatibility, Case No. 246 (Northwest Marana Reliability Project), with Exhibit A map (docketed 2025-06-25), pp.2-5; p.16 · TEP, Grier Substation project page (n/a (retrieved 2026-11-20)), Project Description. Researched by Substation Scout; checked November 21, 2026.

The project in the plan

ProjectWhere in the planLine siting case
Loop-in of Tortolita - North Loop Line #4 into Planned Grier 138-kV Substationp.54Case No. 246

Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.