Wafer
In the Arizona Public Service ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation new. “The 500kV lines will be brought overhead into the new substation and the 230kV lines will be brought into the substation underground.” — APS 2026-2035 Ten Year Transmission Plan, p.33
The same paragraph (p.33) begins "The Wafer substation is planned to be located generally northeast of the intersection of 51st Avenue and Dove Valley Road"; the sheet's Point of Termination is "Wafer substation (in-service 2028)".
Also mentioned: “Decision No. 78251, on 9/29/2021, amended the CEC authorizing the cut-in and construction of a third substation (Wafer) along the lines.” — APS 2026-2035 Ten Year Transmission Plan, p.33 · “and the future Wafer substation.” — APS 2026-2035 Ten Year Transmission Plan, p.75 · “Wafer 500kV and 230kV Lines and Wafer 500/230kV Substation” — APS 2026-2035 Ten Year Transmission Plan, p.78 · “The TS22 substation is now named Wafer.” — APS 2026-2035 Ten Year Transmission Plan, p.14 · “Wafer 230/69kV Transformer Addition (1 unit)” — APS 2026-2035 Ten Year Transmission Plan, p.11
Note. Formerly listed as TS22 (plan p.14).
Note. The plan gives the purpose as "To provide electric energy to a high-load customer and support planned growth in the Biscuit Flats area of north Phoenix."
Note. ACC Decision No. 78251 (2021-09-29, https://docket.images.azcc.gov/0000204835.pdf, retrieved 2026-11-20), which authorized this third substation on CEC 131 (then called TS22), says the changes "are needed to serve the operation of the TSMC Semiconductor Plant".
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
Maricopa County, AZ
County of the land section printed for it. A filing prints the section, township and range for this substation, and that one-square-mile section lies in one county. No point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. The plan's "generally northeast of the intersection of 51st Avenue and Dove Valley Road" is a direction, not a site; the CEC prints a ~475-acre TS22 Substation Siting Area (from 1.2 miles west to 0.5 mile east of the 51st Avenue alignment, 1,320-3,805 feet north of Dove Valley Road) for an ~80-acre substation, and printed coordinates (33°47'25" N, 112°10'47" W) only for the line's in-and-out interconnection point, which is west of 51st Avenue while the plan now puts the station north-east of it. Lead not adopted: an unnamed 230 kV OSM substation (way 1232317680, 33.7799, -112.1741) lies south of Dove Valley Road and west of 51st Avenue, on the TSMC side, so it does not fit.
County: the filing prints “"to a point (Latitude 33°47'25" North Longitude -112°10'47"), along the half-section line of Section 8, Township 5 North, Range 2 East G&SRB&M between SR 74 and the Dove Valley Road Alignment where the line would form an in and out interconnection to the TS22 Substation"”, a section in Maricopa County.
Sources: APS 2026-2035 Ten Year Transmission Plan (Arizona Public Service Company), ACC Docket E-99999A-25-0006 (A.R.S. 40-360.02 ten-year plans) (filed 2026-01-30), p.33 · ACC Decision No. 78251 amending CEC 131 (Morgan-Pinnacle Peak) and CEC 120, TS22 substation, Dockets L-00000D-06-0635-00131 and L-00000D-02-0120-00120 (2021-09-29), pp.4-5 · APS CEC 131 annual compliance filing, Decision No. 78251 (filed 2025-11-13), p.1 · BLM National PLSS CadNSDI (PLSS Township and Section layers), section polygon lookup (n/a (queried 2026-11-21)), layers 1-2. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Wafer 500kV and 230kV Lines | p.33 | CEC 131 |
Generation interconnection requests filed in Maricopa, AZ: APS queue, 82 active of 259. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.