Pohatcong substation interconnection queue

1 active project totaling 80 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Pohatcong as the point of interconnection, all in Warren County, NJ.

Target commercial operation dates as filed run from Jun 2023 to Oct 2029 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: JCPL (1 filing).

1active projects
80active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-2106 Pohatcong 34.5 kV 34.5 80 Battery Active Oct 2029
AF1-107 Pohatcong 230 kV 230 60 Battery Withdrawn Jun 2023

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Pohatcong (JCPL, 3 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Warren County, NJ

All 113 PJM queue filings in Warren County, NJ, including 4 more substations.