Mansfield substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 4 with terminal status (shown grayed).
Target commercial operation dates as filed run from Oct 2011 to Dec 2023 (3 filings).
0active projects
0active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| D24 | Mansfield 115kV | 115 | 500 | Gas | Withdrawn | n/r |
| AG2-614 | Mansfield 12 kV | 12 | 4.3 | Solar | Withdrawn | Dec 2023 |
| X1-008 | Mansfield | n/r | 2.9 | Solar | Withdrawn | Oct 2011 |
| X3-035 | Mansfield | n/r | 0 | Solar | Withdrawn | Jul 2012 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Tioga County, PA
- Warfordsburg: 1 active, 12 MW of 2 filed
- Mainesburg: none active of 3 filed
- Sabinsville: none active of 3 filed
- Tower Hill: none active of 3 filed
Other PJM queue substations in Warren County, NJ
- Pequest River: 3 active, 165.9 MW of 5 filed
- Pohatcong: 1 active, 80 MW of 2 filed
- Washington: 3 active, 53.3 MW of 3 filed
- Kittatinny: 1 active, 20 MW of 3 filed
- Phillipsburg: 2 active, 4.1 MW of 8 filed
- Washington-Mobile Chemical: 1 active, 3.8 MW of 2 filed
- Stewartsville: 1 active, 3.6 MW of 2 filed
- Broadway-Stewartsville: 2 active, 3.3 MW of 2 filed
- Gilbert-Morris Park: 1 active, 3.2 MW of 4 filed
- Foul Rift: 1 active, 0.8 MW of 2 filed
- Columbia: 1 active, 0.5 MW of 4 filed
- Belvidere: 1 active, 0 MW of 5 filed
- Morris Park: none active of 4 filed
- Andover-Kittatinny: none active of 3 filed
- Broadway: none active of 3 filed
- Newburgh: none active of 3 filed
- Flanders: none active of 2 filed
- Franklin #2: none active of 2 filed
- Hackettstown: none active of 2 filed
- Lopatcong: none active of 2 filed
All 113 PJM queue filings in Warren County, NJ, including 4 more substations.