Stewartsville substation interconnection queue
1 active project totaling 3.6 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Stewartsville as the point of interconnection, all in Warren County, NJ.
Target commercial operation dates as filed run from Jun 2011 to Dec 2016 (2 filings).
1active projects
3.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| V2-010 | Stewartsville 34.5kV | 34.5 | 3.8 | Solar | Withdrawn | Jun 2011 |
| AB2-058 | Stewartsville Solar Farm | 34.5 | 3.6 | Solar | In Service | Dec 2016 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Warren County, NJ
- Pequest River: 3 active, 165.9 MW of 5 filed
- Pohatcong: 1 active, 80 MW of 2 filed
- Washington: 3 active, 53.3 MW of 3 filed
- Kittatinny: 1 active, 20 MW of 3 filed
- Phillipsburg: 2 active, 4.1 MW of 8 filed
- Washington-Mobile Chemical: 1 active, 3.8 MW of 2 filed
- Broadway-Stewartsville: 2 active, 3.3 MW of 2 filed
- Gilbert-Morris Park: 1 active, 3.2 MW of 4 filed
- Foul Rift: 1 active, 0.8 MW of 2 filed
- Columbia: 1 active, 0.5 MW of 4 filed
- Belvidere: 1 active, 0 MW of 5 filed
- Mansfield: none active of 4 filed
- Morris Park: none active of 4 filed
- Andover-Kittatinny: none active of 3 filed
- Broadway: none active of 3 filed
- Newburgh: none active of 3 filed
- Flanders: none active of 2 filed
- Franklin #2: none active of 2 filed
- Hackettstown: none active of 2 filed
- Lopatcong: none active of 2 filed
All 113 PJM queue filings in Warren County, NJ, including 4 more substations.