Named in 2 PJM planning documents for 2 projects, from January 7, 2025 to June 5, 2025.

Newdescribed as
PJM system-widezone
765 kVkV as printed
2mentions

Described as new: “Construct a new 765 kV switchyard (Welton Spring)” — source, page 63

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Recommended Solution: 2024-W1-708
b4000.1
Not printed $1,945.05 M 12/1/2029 Not printed 2025-01-07
TEAC
2024 W1 Regional Cluster: Baseline b4000.6 Project Update
b4000.6
Not printed $353.5 M 6/1/2029 Not printed 2025-06-05
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-06-05 TEAC
Item 09 - Reliability Analysis Update p. 51
2024 W1 Regional Cluster: Baseline b4000.6 Project Update No role wording
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 63
Recommended Solution: 2024-W1-708 “Construct a new 765 kV switchyard (Welton Spring)”
765 kV