Substation Scout

LOUDON

Named in 1 PJM planning document for 1 project, on December 5, 2023.

Not stateddescribed as
PJM system-widezone
230kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
APS Area and Dominion Area - Short Circuit Upgrades
b3800.401
Not printed $63.27M Not printed Not printed 2023-12-05
TEAC

Other substations in this project

“APS Area and Dominion Area - Short Circuit Upgrades” also names 12 other substations, with what the most recent document says about each.

Every mention

DateDocumentProjectWhat the document says about it
2023-12-05 TEAC
Item 15 - Reliability Analysis Update 2022 Window 3 p. 69
APS Area and Dominion Area - Short Circuit Upgrades No role wording
230

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.