Dickerson H
Named in 1 PJM planning document for 1 project, on December 5, 2023.
Same name on other Substation Scout pages
Other sources that print a substation named “Dickerson H”. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Dickerson Station H: Expansion Tracker, PJM planning: PJM system-wide state not printed
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of a named transmission project: 2022 Window 3 Northern Virginia/Doubs Cluster ($1,418.3M).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster B3800.243 – B3800.245 |
Not printed | $66.38 M | 2028-2030 | Not printed | 2023-12-05 TEAC |
Other substations in this project
“2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster” also names 4 other substations, with what the most recent document says about each.
- Dickerson Station H PJM system-wide Work described at it — “Rebuild 7.26 miles of existing 230 kV circuit from Dickerson Station H to Ed's Ferry area” (p. 47)
- Doubs PJM system-wide Work described at it
- Ed's Ferry PJM system-wide Not stated
- Goose Creek PJM system-wide Work described at it
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 47 |
2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | “Reconfigure Dickerson H 230 kV Substation and upgrade terminal equipment.” 230 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.