Goose Creek
Named in 4 PJM planning documents for 4 projects, from December 5, 2023 to October 6, 2026.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Extend the existing 500kV ring bus at Goose Creek Substation” — source, page 9
Also printed as: Goose Creek Substation
Same name on other Substation Scout pages
Other sources that print a substation named “Goose Creek”. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Goose Creek: Expansion Tracker, PJM planning: APS state not printed
- Goose Creek: Expansion Tracker, PJM planning: PJM system-wide state not printed
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of named transmission projects: 2022 Window 3 West Cluster Incumbent Upgrades ($392.55M), 2022 Window 3 Northern Virginia/Doubs Cluster ($1,418.3M).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion) b3800.118, b3800.120 & b3800.375 |
Not printed | $73.94M | 9/30/2030 (b3800.120 & b3800.375), 6/1/2028 (b3800.118) | Not printed | 2026-10-06 TEAC |
| 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster B3800.200 – B3800.227 |
Not printed | $1025.06 M | 6/1/2028 | Not printed | 2023-12-05 TEAC |
| 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster B3800.230 – B3800.242 |
Not printed | $78.4 M | 12/1/2027 | Not printed | 2023-12-05 TEAC |
| Do No Harm Analysis DOM-2021-0016-DNH · s2609.2 |
In service | $40.0 M | 12/15/2023 | Not printed | 2024-10-08 TEAC |
Other substations in these projects
The 4 projects above also name 34 other substations, with what the most recent document says about each.
- Aspen DOM New — “moved to Aspen substation” (p. 7) (in 3 of the 4 projects)
- Pleasant View DOM Work described at it — “Upgrade 230kV Pleasant View breakers” (p. 17) (in 3 of the 4 projects)
- Beaumeade DOM Work described at it — “Replace overdutied breakers at Belmont, BECO, Beaumeade” (p. 41) (in 2 of the 4 projects)
- Belmont DOM Work described at it — “Replace overdutied breakers at Belmont” (p. 41) (in 2 of the 4 projects)
- Aspen PJM system-wide Work described at it — “Aspen substation work to terminate new NextEra 500 kV line” (p. 65) (in Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion))
- Beco DOM Work described at it — “Equipment upgrades at the following substations: – Paragon Park, BECO” (p. 41) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Bismark PJM system-wide Not stated (in Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion))
- Braddock DOM Not stated (in Do No Harm Analysis)
- Breezy Knoll DOM Work described at it — “Relay resets/revisions at the following substations: – Breezy Knoll” (p. 45) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Clark DOM Not stated (in Do No Harm Analysis)
- Dickerson DOM Not stated (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Discovery DOM Work described at it — “Replace overdutied breakers at Belmont, BECO, Beaumeade, Pleasant View, Shellhorn, and Discovery.” (p. 41) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Doubs PJM system-wide Work described at it (in Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion))
- Doubs DOM Not stated (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Dry Mill DOM Work described at it — “Relay resets/revisions at the following substations: – Breezy Knoll, Dry Mill” (p. 45) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Edwards Ferry DOM Work described at it — “Terminal equipment upgrades at the following substations: – Goose Creek, Pleasant View, Edwards Ferry” (p. 45) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Golden DOM New — “Construct a new Golden 500/230kV substation” (p. 41) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Hamilton Substation DOM Work described at it — “Relay resets/revisions at the following substations: – Breezy Knoll, Dry Mill, Hamilton” (p. 45) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Harrowgate DOM Not stated (in Do No Harm Analysis)
- Hayfield DOM Work described at it (in Do No Harm Analysis)
- Idylwood DOM Not stated (in Do No Harm Analysis)
- Lockridge DOM Work described at it (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Locks DOM Work described at it (in Do No Harm Analysis)
- Loudoun DOM, VA Work described at it — “Replace overdutied breakers at Loudoun” (p. 45) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Mars DOM Work described at it — “Install the 2nd 500-230 kV 1440 MVA transformer at Mars Substation” (p. 41) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Occoquan DOM, VA Work described at it — “leads) at Occoquan Substation” (p. 11) (in Do No Harm Analysis)
- Odgen Martin DOM Not stated (in Do No Harm Analysis)
- Paragon Park DOM Work described at it — “Equipment upgrades at the following substations: – Paragon Park, BECO” (p. 41) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Possum Point DOM, VA Work described at it (in Do No Harm Analysis)
- Shellhorn DOM Work described at it — “Replace overdutied breakers at Belmont, BECO, Beaumeade, Pleasant View, Shellhorn” (p. 41) (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Sycolin Creek DOM New (in 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster)
- Tyler DOM Not stated (in Do No Harm Analysis)
- Woodside DOM Work described at it — “terminating Doubs to Bismark line into Woodside 500 kV substation” (p. 7) (in Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion))
- Woodside PJM system-wide Work described at it (in Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion))
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $35.59M → $73.94M | 2023-12-05 | 2026-10-06 |
| Cost estimate prior value printed on the same page |
$51.19M → $73.94M | 2026-10-06 | 2026-10-06 |
| In-service date | 6/1/2027 → 9/30/2030 (b3800.120 & b3800.375), 6/1/2028 (b3800.118) | 2023-12-05 | 2026-10-06 |
| Substations named | ASPEN; BISMARK; DOUBS; WOODSIDE → ASPEN; GOOSE CREEK; WOODSIDE | 2023-12-05 | 2026-10-06 |
| Cost estimate | 138.5 M → $40.0 M | 2026-11-03 | Not reported |
| Cost estimate | $40.0 M → 138.5 M | 2024-10-08 | 2026-11-03 |
| Cost estimate prior value printed on the same page |
$84.9 M → 138.5 M | 2026-11-03 | 2026-11-03 |
| In-service date | 06/01/2029 → 12/15/2023 | 2026-11-03 | Not reported |
| In-service date | 12/15/2023 → 06/01/2029 | 2024-10-08 | 2026-11-03 |
| Status | engineering (Engineering) → in-service (In-Service) | 2026-11-03 | Not reported |
| Status | in-service (In-Service) → engineering (Engineering) | 2024-10-08 | 2026-11-03 |
| Substations named | BRADDOCK; HAYFIELD; OCCOQUAN; ODGEN MARTIN; POSSUM POINT → BEAUMEADE; BELMONT; CLARK; GOOSE CREEK; HARROWGATE; IDYLWOOD; LOCKS; PLEASANT VIEW; TYLER | 2026-11-03 | Not reported |
| Substations named | BEAUMEADE; BELMONT; CLARK; GOOSE CREEK; HARROWGATE; IDYLWOOD; LOCKS; PLEASANT VIEW; TYLER → BRADDOCK; HAYFIELD; OCCOQUAN; ODGEN MARTIN; POSSUM POINT | 2024-10-08 | 2026-11-03 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Item 16 - Reliability Analysis Update - Presentation p. 7 |
Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion) | “Terminate new NextEra 500 kV line from Woodside into Goose Creek substation” 500kV |
| 2026-09-08* | SRRTEP Southern Dominion local plan submission of the supplemental projects for 2024 p. 9 |
Do No Harm Analysis | “Extend the existing 500kV ring bus at Goose Creek Substation” 500-230 kV |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 9 |
Do No Harm Analysis | “Extend the existing 500kV ring bus at Goose Creek Substation” 500-230 kV |
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 41 |
2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | No role wording 500kV |
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 45 |
2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | “Terminal equipment upgrades at the following substations:
– Goose Creek, Pleasant View, Edwards Ferry” 500kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.