Stonewall/Woodside
Named in 1 PJM planning document for 1 project, on December 5, 2023.
Described as new. The quoted wording calls this substation new. “New Stonewall/Woodside substation” — source, page 63
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of a named transmission project: MidAtlantic Resiliency Link (MARL) ($844.80M).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Preferred Proposals to Address Clusters - West b3800.102, b3800.106 - b3800.110, b3800.113, b3800.115, b3800.117 & b3800.119 |
Not printed | $512.61M | 6/1/2027 | Not printed | 2023-12-05 TEAC |
Other substations in this project
“Preferred Proposals to Address Clusters - West” also names 8 other substations, with what the most recent document says about each.
- 502 Junction PJM system-wide Work described at it — “existing 502 Junction substation” (p. 66)
- Aspen PJM system-wide Work described at it
- Bismark PJM system-wide Not stated
- Black Oak PJM system-wide Expansion — “bypass Black Oak” (p. 66)
- Doubs PJM system-wide Work described at it
- Gore PJM system-wide Not stated
- Stonewall PJM system-wide Work described at it — “existing Stonewall 138 kV substation” (p. 66)
- Woodside PJM system-wide Work described at it — “Woodside substation adjacent to existing Stonewall 138 kV substation” (p. 66)
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$440.95M → $844.80M | 2026-01-06 | 2026-01-06 |
| Cost estimate | $512.61M → $844.80M | 2023-12-05 | 2026-01-06 |
| In-service date | 6/1/2027 → December 2028 | 2023-12-05 | 2026-01-06 |
| Substations named | 502 JUNCTION; ASPEN; BISMARK; DOUBS; STONEWALL; STONEWALL WOODSIDE; WOODSIDE → 502 JUNCTION; BISMARK; BLACK OAK; DOUBS; GORE; STONEWALL; WOODSIDE | 2023-12-05 | 2026-01-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 63 |
Preferred Proposals to Address Clusters - West | “New Stonewall/Woodside substation” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.