Doubs substation interconnection queue
2 active projects totalling 450 MW in the PJM queue, plus 3 with terminal status (shown greyed).
2active projects
450active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1767 | Doubs 230 kV | 230 | 350 | Battery | Active |
| C01-1478 | Doubs 230 kV | 230 | 140 | Battery | Withdrawn |
| C01-2012 | Doubs 230 kV | 230 | 100 | Battery | Active |
| AC1-139 | Doubs 230kV | 230 | 38.8 | Solar | Withdrawn |
| AB2-129 | Potomac Solar, LLC | 230 | 30.4 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.