Welton Springs

Named in 1 PJM planning document for 1 project, on December 3, 2024.

Newdescribed as
PJM system-widezone
765 kVkV as printed
1mentions

Described as new: “Construct a new switchyard (Welton Springs)” — source, page 78

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708
2024-W1-708
Not printed $1,944.98 M 12/1/2029 Not printed 2024-12-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 78
2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 “Construct a new switchyard (Welton Springs)”
765 kV