Otter Creek
Named in 1 PJM planning document for 2 projects, on December 5, 2023.
Described as new. The quoted wording calls this substation new. “Build New Otter Creek 500 kV switching station” — source, page 57
Same name on other Substation Scout pages
Other sources that print a substation named “Otter Creek”. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Otter Creek: Expansion Tracker, PJM planning: METED state not printed
- Otter Creek: Expansion Tracker, PJM planning: PPL state not printed
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of a named transmission project: Maryland Piedmont Reliability Project (MPRP): Chanceford - Doubs 500 kV ($447.5M (PSEG)).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Recommended Solutions to Address Clusters - East B3800.1 –B3800.6 |
Not printed | $134.2 M | 6/1/2027 | Not printed | 2023-12-05 TEAC |
| Recommended Solutions to Address Clusters - East B3800.7 –B3800.8 and B3800.43 |
Not printed | $447.5 M | 6/1/2027 | Not printed | 2023-12-05 TEAC |
Other substations in these projects
The 2 projects above also name 10 other substations, with what the most recent document says about each.
- Conastone PJM system-wide Work described at it — “towards Conastone station fence” (p. 57) (in 2 of the 2 projects)
- Chanceford PPL New — “Build new Otter Creek 500 kV (Chanceford) Switching Station” (p. 18) (in Recommended Solutions to Address Clusters - East)
- Conastone PPL Work described at it — “Rebuild the existing Otter Creek - Conastone 230 kV line to become a double-circuit 500 kV line, operate Conastone circuit at 230 kV initially” (p. 18) (in Recommended Solutions to Address Clusters - East)
- Doubs PPL Not stated (in Recommended Solutions to Address Clusters - East)
- Doubs PJM system-wide Work described at it — “Reconfigure Doubs 500 kV station and upgrade terminal equipment” (p. 58) (in Recommended Solutions to Address Clusters - East)
- Otter Creek PPL New — “Build new Otter Creek 500 kV (Chanceford) Switching Station” (p. 18) (in Recommended Solutions to Address Clusters - East)
- Peach Bottom PPL Work described at it — “from the existing TMI-Peach Bottom 500 kV right-of-way” (p. 18) (in Recommended Solutions to Address Clusters - East)
- Peach Bottom PJM system-wide Work described at it — “Upgrade relay/terminal equipment at Peach Bottom and TMI substations” (p. 57) (in Recommended Solutions to Address Clusters - East)
- TMI PPL, PA Work described at it — “from the existing TMI-Peach Bottom 500 kV right-of-way” (p. 18) (in Recommended Solutions to Address Clusters - East)
- TMI PJM system-wide Work described at it — “Upgrade relay/terminal equipment at Peach Bottom and TMI substations” (p. 57) (in Recommended Solutions to Address Clusters - East)
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $134.2 M → $148.15 M | 2023-12-05 | 2025-07-08 |
| Cost estimate prior value printed on the same page |
$148.15M → $148.15 M | 2025-07-08 | 2025-07-08 |
| Substations named | CONASTONE; OTTER CREEK; PEACH BOTTOM; TMI → CHANCEFORD; CONASTONE; DOUBS; OTTER CREEK; PEACH BOTTOM; TMI | 2023-12-05 | 2025-07-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 57 |
Recommended Solutions to Address Clusters - East | “Build New Otter Creek 500 kV switching station” 500 kV |
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 58 |
Recommended Solutions to Address Clusters - East | No role wording 500 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.