Penns Neck substation interconnection queue

1 active project totalling 0 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
V3-050 Penns Neck 13kV 13 4.6 Gas Withdrawn
AA2-066 Princeton Hospital NRG Energy Center 13 0 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.