Devils Brook substation interconnection queue
3 active projects totaling 3.9 MW in the PJM queue.
3 PJM queue filings name Devils Brook as the point of interconnection, all in Middlesex County, NJ.
Target commercial operation dates as filed run from Jun 2011 to Sep 2012 (3 filings).
3active projects
3.9active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| V3-024 | RE Cranbury Solar I, LLC | 13.2 | 1.9 | Solar | In Service | Sep 2011 |
| W3-124 | Matrix-Stults Road | 13 | 1.1 | Solar | In Service | Jun 2011 |
| X2-088 | Black Rock Solar | 13 | 0.9 | Solar | In Service | Sep 2012 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Middlesex County, NJ
- Sewaren: 4 active, 2,007.2 MW of 13 filed
- Sayreville: 2 active, 1,555 MW of 8 filed
- Raritan River: 4 active, 1,060 MW of 8 filed
- Kearny: 8 active, 931 MW of 12 filed
- Brunswick: 4 active, 153.8 MW of 6 filed
- Parlin: 1 active, 102 MW of 4 filed
- Red Oak: 3 active, 90.5 MW of 8 filed
- South River: 2 active, 47 MW of 6 filed
- Howell: 1 active, 6.5 MW of 2 filed
- Monroe: 1 active, 4.9 MW of 2 filed
- Metuchen: 1 active, 2.5 MW of 6 filed
- Pierson Avenue: 2 active, 1 MW of 2 filed
- Edison 4kV: 1 active, 0.2 MW of 2 filed
- Branchburg-Deans: none active of 4 filed
- Deans: none active of 4 filed
- Edison: none active of 4 filed
- Somerville: none active of 3 filed
- Atlantic-South River: none active of 2 filed
- Cranbury: none active of 2 filed
- Deep Run: none active of 2 filed
All 120 PJM queue filings in Middlesex County, NJ, including 3 more substations.