Substation Scout

Trenton substation interconnection queue

1 active project totaling 3 MW in the PJM queue, plus 5 with terminal status (shown grayed).

Target commercial operation dates as filed run from Jun 2012 to Jan 2016 (6 filings).

1active projects
3active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
X2-014 Hedding Road Solar 26 3.8 Solar Withdrawn Jun 2013
W4-075 CleanLight Mansfield Solar Project 26 3.4 Solar Withdrawn Jun 2012
Z1-096 Parkland Solar 26 3 Solar In Service Dec 2014
X2-033 Ward Avenue Solar 26 1.1 Solar Withdrawn Jun 2013
AB1-118 Trenton 13kV 13 0.7 Gas Withdrawn Jan 2016
Y1-063 Trenton 34.5kV 34.5 0 Battery Deactivated Mar 2014

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Burlington County, NJ

All 118 PJM queue filings in Burlington County, NJ, including 2 more substations.

Other PJM queue substations in Mercer County, NJ

All 28 PJM queue filings in Mercer County, NJ.

Other PJM queue substations in Delaware County, OH

No other substation in Delaware County, OH is named as a point of interconnection in the PJM queue.

All 5 PJM queue filings in Delaware County, OH.