Windsor substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 5 with terminal status (shown grayed).
Target commercial operation dates as filed run from Jun 2005 to Dec 2027 (5 filings).
0active projects
0active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| H08_W66 | Windsor 138 kV | 138 | 300 | Gas | Withdrawn | Jun 2005 |
| AF2-071 | Windsor 230 kV | 230 | 100 | Battery | Withdrawn | Mar 2023 |
| AI1-180 | Windsor 69 kV | 69 | 100 | Hybrid | Withdrawn | Dec 2027 |
| AH1-118 | Windsor 25 kV | 25 | 12 | Solar | Withdrawn | Dec 2023 |
| N37 | Windsor 138kV | 138 | 10 | Wind | Withdrawn | Nov 2006 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Mercer County, NJ
- Pleasant Valley: 3 active, 800 MW of 5 filed
- Hopewell: 3 active, 188 MW of 12 filed
- Mercer: 2 active, 180 MW of 5 filed
- Crosswicks: 2 active, 161 MW of 3 filed
- Trenton: 1 active, 3 MW of 6 filed
- Lawrence: 1 active, 0.3 MW of 4 filed
- Mount Rose: 1 active, 0.3 MW of 2 filed
- Yardville: none active of 3 filed
- Penns Neck: 1 active, 0 MW of 2 filed
- Princeton University: 1 active, 0 MW of 2 filed
Other PJM queue substations in Brooke County, WV
- Tidd-Wylie Ridge: none active of 3 filed
Other PJM queue substations in Washington County, PA
- Clinton: 3 active, 949.4 MW of 5 filed
- Wilson: 1 active, 300 MW of 6 filed
- Vanceville: 1 active, 200 MW of 2 filed
- Byron: 1 active, 43 MW of 3 filed
- Motion-Ridgeway: 1 active, 12 MW of 2 filed
- Clinton II: 1 active, 3.2 MW of 2 filed
- Champion: none active of 3 filed
- Wylie Ridge: none active of 3 filed
- Hunterstown-Jackson: none active of 2 filed
- Smith-N. Fayette: none active of 2 filed
Site Scanner