Substation Scout

Branchburg-Deans substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 4 with terminal status (shown grayed).

4 PJM queue filings name Branchburg-Deans as the point of interconnection, all in NJ.

Target commercial operation dates as filed run from Jun 2014 to Jun 2021 (4 filings).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AA2-142 Branchburg-Deans 500kV 500 1,278 Gas Withdrawn Jun 2021
U2-005 Branchburg-Deans 500kV 500 1,010 Gas Withdrawn Jun 2014
U2-006 Branchburg-Deans 500kV 500 1,010 Gas Withdrawn Jun 2015
AB1-148 Branchburg-Deans 500kV 500 235 Gas Withdrawn Jun 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Somerset County, NJ

All 14 PJM queue filings in Somerset County, NJ.

Other PJM queue substations in Middlesex County, NJ

All 120 PJM queue filings in Middlesex County, NJ, including 3 more substations.