Substation Scout

Branchburg-Deans substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 4 with terminal status (shown greyed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
AA2-142 Branchburg-Deans 500kV 500 1,278 Gas Withdrawn
U2-005 Branchburg-Deans 500kV 500 1,010 Gas Withdrawn
U2-006 Branchburg-Deans 500kV 500 1,010 Gas Withdrawn
AB1-148 Branchburg-Deans 500kV 500 235 Gas Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.