Substation Scout

Sewaren substation interconnection queue

5 active projects totalling 2,032.2 MW in the PJM queue, plus 8 with terminal status (shown greyed).

5active projects
2,032.2active MW
13total filed
Queue IDProjectkVMWResourceStatus
C01-1086 Sewaren 230 kV 230 1,389 Gas Active
AE2-014 Sewaren 230 kV 230 1,200 Wind Withdrawn
J08_MTX15 Sewaren 230kV 230 790 Not reported Withdrawn
W2-023 Sewaren 230kV 230 625 Gas Withdrawn
AA2-124 Sewaren 230kV 230 553 Gas Withdrawn
Z2-089 Sewaren 7 230 541 Gas In Service
Y1-011 Sewaren 230kV 230 520 Gas Withdrawn
A14 Sewaren n/r 500 Gas Withdrawn
G15 Sewaren n/r 300 Gas Withdrawn
E10 Sewaren 230kV 230 162 Gas Withdrawn
C01-1493 Sewaren 230 kV 230 45.2 Gas Active
AA2-099 Sewaren 7 230 32 Gas In Service
C01-1246 Sewaren 26 kV 26 25 Battery Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.