Substation Scout

Red Oak substation interconnection queue

4 active projects totalling 125.5 MW in the PJM queue, plus 4 with terminal status (shown greyed).

4active projects
125.5active MW
8total filed
Queue IDProjectkVMWResourceStatus
Q11 Red Oak 230kV 230 300 Gas Withdrawn
R39 Red Oak 230kV 230 300 Gas Withdrawn
C01-1357 Red Oak 230 kV 230 71.5 Battery Active
Q08 Red Oak 230kV 230 50 Gas Withdrawn
V3-034 Red Oak 230kV 230 50 Gas Withdrawn
C01-2018 Red Oak 230 kV 230 35 Gas Active
X1-068 Red Oak 230 10 Gas In Service
AE1-036 Red Oak 230 9 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.