Parlin substation interconnection queue
1 active project totalling 102 MW in the PJM queue, plus 3 with terminal status (shown greyed).
1active projects
102active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| S25 | Calpine Parlin Energy Center | 230 | 114 | Gas | Deactivated |
| C01-1075 | Parlin 230 kV | 230 | 102 | Gas | Active |
| E24 | Parlin 230kV | 230 | 100 | Gas | Withdrawn |
| AA2-122 | Parlin 230kV | 230 | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.