Princeton Hospital NRG Energy Center
PJM queue ID AA2-066
Princeton Hospital NRG Energy Center (AA2-066) is listed in the PJM interconnection queue as a gas request filed at 0 MW (a net change or energy-only filing) in Mercer County, NJ. The filing names Penns Neck as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2016.
| Queue ID | AA2-066 |
|---|---|
| Project name | Princeton Hospital NRG Energy Center |
| Status (as published) | In Service |
| Substation | Penns Neck |
| Point of interconnection | Penns Neck 13kV |
| County | Mercer |
| State | NJ |
| Voltage | 13 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2016-06-01 |
| Source dataset | serial |
Same substation and county
Penns Neck substation: 2 requests in the PJM queue, 1 active totaling 0 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| V3-050 | Penns Neck 13kV | 4.6 | Gas | Withdrawn |
Mercer, NJ: 28 requests in the PJM queue, 8 active totaling 183.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 2 |
| MW capacity | 0 |
| MFO | 2 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.