Mendota substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 4 with terminal status (shown greyed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
U4-006 Mendota 138kV 138 20 Other Withdrawn
W4-019 Mendota n/r 9.8 Wind Withdrawn
P24 Mendota 34.5kV 34.5 4 Wind Withdrawn
P25 Mendota 34.5kV 34.5 4 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.