Nelson-Lee County substation interconnection queue

1 active project totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).

1active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
AH2-122 Nelson-Lee County 345 kV 345 100 Battery Withdrawn
AF2-183 Nelson-Lee County 345 kV 345 32 Battery Withdrawn
AF1-281 Nelson-Lee County n/r 3 Battery Withdrawn
AF1-280 South Dixon Solar n/r 0 Solar EP

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.