Lee County substation interconnection queue

1 active project totalling 48 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
48active MW
3total filed
Queue IDProjectkVMWResourceStatus
AC1-185 Lee Energy Facility n/r 48 Gas In Service
T106 Lee County n/r 28 Wind Withdrawn
V3-014 Lee County n/r 20.8 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.