Substation Scout

Katydid Road substation interconnection queue

4 active projects totaling 185.1 MW in the PJM queue, plus 1 with terminal status (shown grayed).

5 PJM queue filings name Katydid Road as the point of interconnection, all in IL.

Target commercial operation dates as filed run from Jun 2022 to Mar 2029 (5 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: ComEd (4 filings).

4active projects
185.1active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1422 Katydid Road 345 kV 345 96 Wind Active Jun 2026
AF1-316 Katydid Road 345 kV 345 52.8 Solar Withdrawn Jun 2022
C01-1423 Katydid Road 345 kV 345 49.1 Wind Active Jun 2026
AF2-226 Top Crop Generating Facility 345 20 Battery EP Mar 2029
AF2-319 Top Crop Generating Facility 345 20 Battery EP Mar 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Livingston County, IL

All 47 PJM queue filings in Livingston County, IL.

Other PJM queue substations in Grundy County, IL

All 44 PJM queue filings in Grundy County, IL.

Other PJM queue substations in Lasalle County, IL

All 27 PJM queue filings in Lasalle County, IL.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first