Shady Oaks substation interconnection queue
1 active project totalling 21.2 MW in the PJM queue, plus 1 with terminal status (shown greyed).
1active projects
21.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG1-128 | Shady Oaks 138 kV | 138 | 51.8 | Wind | Withdrawn |
| AD2-134 | Shady Oaks Wind Power Project | n/r | 21.2 | Wind | Partially in Service - Under Construction |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.