Nevada substation interconnection queue
1 active project totaling 90 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Nevada as the point of interconnection, all in Lasalle County, IL.
Target commercial operation dates as filed run from Dec 2020 to May 2029 (2 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: ComEd (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-142 | Otter Creek Solar | 345 | 90 | Solar | EP | May 2029 |
| AD1-116 | Nevada 345 kV | 345 | 7.6 | Solar | Withdrawn | Dec 2020 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Nevada (COMED, 4 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Lasalle County, IL
- LaSalle: 4 active, 584 MW of 8 filed
- Katydid Road: 4 active, 185.1 MW of 5 filed
- Powerton-Nevada: 4 active, 172.4 MW of 4 filed
- LaSalle 1: 1 active, 11.9 MW of 2 filed
- Mendota: none active of 4 filed
- Crescent Ridge-Corbin: none active of 2 filed
- LaSalle-Braidwood: none active of 2 filed
- Tazewell - AB1-122: none active of 2 filed