Substation Scout

Nelson - Electric Junction substation interconnection queue

1 active project totalling 120 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
120active MW
3total filed
Queue IDProjectkVMWResourceStatus
AH1-044 Nelson - Electric Junction 345 kV 345 120 Solar Active
C01-1671 Nelson - Electric Junction 345 kV 345 120 Solar Withdrawn
C01-1672 Nelson - Electric Junction 345 kV 345 120 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.