Katydid Road 345 kV (C01-1422) is listed in the PJM interconnection queue as a 96 MW wind project in Livingston County, IL. The filing names Katydid Road as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 23, 2026.

Queue IDC01-1422
Project nameKatydid Road 345 kV
Status (as published)Active
SubstationKatydid Road
Point of interconnectionKatydid Road 345 kV
CountyLivingston
StateIL
Voltage345 kV
Capacity96 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2026-06-23
Source datasetcycle

Same substation and county

Katydid Road substation: 5 requests in the PJM queue, 4 active totaling 185.1 MW.

Queue IDProjectMWResourceStatus
C01-1423Katydid Road 345 kV49.1WindActive
AF2-226Top Crop Generating Facility20BatteryEP
AF2-319Top Crop Generating Facility20BatteryEP
AF1-316Katydid Road 345 kV52.8SolarWithdrawn

Livingston, IL: 47 requests in the PJM queue, 13 active totaling 1,544.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperBLACKSTONE WIND FARM II LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy0.0
MW capacity96.0
MFO300.0
Submitted date4/27/2026
Last updated7/6/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first