McLean substation interconnection queue

4 active projects totalling 264 MW in the PJM queue, plus 1 with terminal status (shown greyed).

4active projects
264active MW
5total filed
Queue IDProjectkVMWResourceStatus
C01-1164 McLean 345 kV 345 97.5 Wind Active
AE1-205 Blooming Grove Solar Energy Center 345 84 Solar Engineering and Procurement
AF2-225 Bright Stalk Generating Facility 345 63 Solar EP
AE2-173 Blooming Grove Solar Energy Center 345 50 Battery Withdrawn
AE2-223 Bright Stalk Generating Facility 345 19.5 Wind EP

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.