Substation Scout

Livingston, IL interconnection queue

15 active projects totalling 1,635.9 MW in the PJM queue, plus 32 with terminal status (shown greyed).

15active projects
1,635.9active MW
47total filed
Queue IDProjectkVMWResourceStatus
AH2-416 Pontiac Midpoint 345 n/r 450 Battery Withdrawn
C01-1770 Dresden - Mulberry 345 kV 345 432.9 Solar Active
AH1-755 Not reported n/r 330 Hybrid Withdrawn
AH2-415 Pontiac Midpoint 345 kV 345 300 Battery Withdrawn
C01-2184 Pontiac - Dresden 345 kV 345 288.6 Solar Active
C01-1098 Dresden - Ponitac Midpoint 345 kV 345 185 Hybrid Active
AH1-633 Powerton to Katydid 345 kV 345 172.8 Solar Withdrawn
AH2-113 Dresden – Pontiac Midpoint 345kV 345 170 Hybrid Withdrawn
C01-2175 Essex (AD1-100) - Loretto 345 kV 345 160 Wind Withdrawn
C01-2189 Pontiac - Dresden 345 kV 345 150 Battery Active
AG1-321 Dresden-Pontiac Midpoint 345 kV 345 126.4 Solar Withdrawn
AD2-177 Pontiac MidPoint 345 kV 345 123 Solar Withdrawn
AI2-106 Pontiac MidPoint-Brokaw 345kV 345 106.4 Solar Withdrawn
R30 Pleasant Ridge Wind Farm 345 100 Wind Withdrawn
AI2-100 Powerton - Dresden 345kv (CIR Increase) 345 96 Wind Withdrawn
C01-1422 Katydid Road 345 kV 345 96 Wind Active
AE1-252 Loretto-Wilton Center n/r 90 Solar Withdrawn
AE1-205 Blooming Grove Solar Energy Center 345 84 Solar Engineering and Procurement
AI2-134 Pontiac Midpoint 345 kV (CIR Increase) 345 84 Solar Withdrawn
AE1-184 Pontiac Midpoint-Dresden n/r 82.7 Not reported Withdrawn
C01-1704 Powerton - Goodings Grove 345 kV 345 80 Wind Active
T105 Pontiac Midpoint-Wilton Center 350 MW n/r 70 Wind Withdrawn
R78 Dresden-Pontiac 345kV 345 60.1 Wind Withdrawn
R79 Tazewell-Kendall 345kV 345 60.1 Wind Withdrawn
AG2-114 Dresden-Pontiac Midpoint 345 kV 345 60 Solar Active
AH1-199 Loretto 345 kV 345 60 Solar Withdrawn
O22 Top Crop Generating Facility 345 60 Wind In Service
O23 Top Crop Wind Farm 345 60 Wind Withdrawn
O24 Bright Stalk WF 345 60 Wind Withdrawn
O27 Powerton-Goodings Grove 345kV 345 60 Gas Withdrawn
O51 Cayuga Ridge South WF 345 60 Wind In Service
W2-046 Powerton-Goodings Grove 345kV 345 58.5 Wind Withdrawn
AB1-024 Loretto-Wilton Ctr n/r 50 Not reported Withdrawn
AI2-099 Powerton-Goodings Grove 345kV (CIR Increase) 345 49.3 Wind Withdrawn
C01-1423 Katydid Road 345 kV 345 49.1 Wind Active
L13_CE27 Heartland Wind Livingston n/r 45 Wind Withdrawn
AE1-172 Livingston Wind n/r 44.9 Wind Withdrawn
C01-1705 Powerton - Goodings Grove 345 kV 345 40 Wind Withdrawn
AB1-029 Loretto-Pontiac n/r 35 Not reported Withdrawn
AH1-543 Mulberry - Tazewell 345 kV 345 31.5 Hybrid Active
Z2-087 Bright Stalk Generating Facility 345 26 Wind In Service
AA1-018 Otter Creek Wind Farm n/r 19.5 Wind In Service
Z2-081 Livingston Landfill Gas to Energy Facility 34.5 13.3 Gas In Service
AG2-147 Pontiac Midpoint 34.5kV 34.5 12 Solar Withdrawn
AC2-152 Pontiac Midpoint n/r 3.8 Solar Withdrawn
X2-092 Cornell 34.5kV 34.5 3.8 Solar Withdrawn
X2-093 Pontiac-Midpoint 34.5kV 34.5 3.8 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.