Substation Scout

Kendall-Tazewell & Dresden-Mole Creek substation interconnection queue

2 active projects totalling 1,243 MW in the PJM queue.

2active projects
1,243active MW
2total filed
Queue IDProjectkVMWResourceStatus
AB1-122 Three Rivers Energy Center n/r 1,150 Gas In Service
AD1-039 Three Rivers Energy Center n/r 93 Gas In Service