Substation Scout

Grundy, IL interconnection queue

21 active projects totalling 3,631.4 MW in the PJM queue, plus 23 with terminal status (shown greyed).

21active projects
3,631.4active MW
44total filed
Queue IDProjectkVMWResourceStatus
S57 Collins n/r 1,500 Wind Withdrawn
AE1-222 Dresden Tazewell Mole Creek n/r 1,270 Gas Withdrawn
AC1-153 Kendall-Tazewell-Dresden-Mole Creek n/r 1,250 Gas Withdrawn
AB1-122 Three Rivers Energy Center n/r 1,150 Gas In Service
AA2-035 Collins n/r 1,019.3 Gas Withdrawn
C01-1808 Collins 345 kV 345 940 Nuclear Active
AA1-048 Kendall n/r 780 Gas Withdrawn
C01-1200 Goodings Gr (B) - Katydid Rd. (B) 345 kV 345 296.2 Hybrid Active
AI1-172 Katydid Road - Goodings Grove 345 kV 345 250 Hybrid Withdrawn
AH2-421 Dresden 138kV 138 230 Battery Withdrawn
C01-1581 Pontiac Red 345kV - Dresden 345 kV 345 210 Solar Active
C01-2001 Dresden - Pontiac Midpoint 345 kV 345 200 Battery Active
AD1-133 Pontiac MidPoint-Dresden n/r 180 Solar Withdrawn
AH2-377 Pontiac Midpoint – Dresden 345 kV 345 150 Battery Withdrawn
C01-1576 Collins 345 kV 345 150 Battery Active
AG2-524 LaSalle Station - Mazon 138 kV 138 110 Hybrid Active
AD1-039 Three Rivers Energy Center n/r 93 Gas In Service
C01-1711 AD2-066 Tap (Hog Run Creek Switchyard ) 138 kV 138 75 Hybrid Active
Q49 Dresden Nuclear Generating Station U2 345 70 Nuclear In Service
Q50 Dresden Nuclear Station Unit 3 345 70 Nuclear In Service
AD2-066 Buffalo Solar 138 69.6 Solar Under Construction
AF1-316 Katydid Road 345 kV 345 52.8 Solar Withdrawn
C01-1577 Collins 345 kV 345 50 Battery Active
AI2-454 Mazon-Oglesby 138kV (CIR Increase) 138 42 Solar Withdrawn
AB1-170 LaSalle-Braidwood n/r 32.5 Wind Withdrawn
C01-1053 Dresden 345 kV 345 32 Nuclear Active
X3-045 Dresden n/r 32 Nuclear Withdrawn
AH2-294 Mazon Blue - Lasalle 138 kV 138 29.5 Solar Withdrawn
AA1-040 Morris Cogen n/r 20 Gas In Service
Y3-088 Kendall Energy Center n/r 20 Gas In Service
Y3-089 Kendall Energy Center n/r 20 Gas In Service
Y3-090 Kendall Energy Center n/r 20 Gas In Service
Y3-091 Kendall Energy Center n/r 20 Gas In Service
AI2-013 Grundy - Goose Lake 138 kV 138 17.2 Solar Withdrawn
AG1-479 Grundy County 34.5 kV II 34.5 15.9 Hybrid Withdrawn
AG1-477 Grundy County 34.5 kV 34.5 14.8 Hybrid Withdrawn
Y2-113 Morris Cogen 138 12.6 Gas In Service
W3-135 Dresden Island Lock & Dam 34.5 12.1 Hydro Withdrawn
C01-1120 Unknown - determine at kickoff 34.5 kV 34.5 9 Hydro Withdrawn
AC2-151 Mazon n/r 7.6 Solar Withdrawn
X1-045 Dresden Nuclear Generation Station, Units 2 & 3 n/r 3 Nuclear In Service
W4-086 Morris Landfill 34.5 2.1 Gas Deactivated
S58 Collins n/r 0 Wind Withdrawn
U3-026 Collins n/r 0 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.