Pontiac - Dresden substation interconnection queue
2 active projects totalling 438.6 MW in the PJM queue.
2active projects
438.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-2184 | Pontiac - Dresden 345 kV | 345 | 288.6 | Solar | Active |
| C01-2189 | Pontiac - Dresden 345 kV | 345 | 150 | Battery | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.