Goose Lake substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Goose Lake as the point of interconnection, all in Grundy County, IL.
Target commercial operation dates as filed run from Mar 2001 to Jan 2022 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| W3-135 | Dresden Island Lock & Dam | 34.5 | 12.1 | Hydro | Withdrawn | Jan 2022 |
| W4-086 | Morris Landfill | 34.5 | 2.1 | Gas | Deactivated | Mar 2001 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Grundy County, IL
- Kendall-Tazewell & Dresden-Mole Creek: 2 active, 1,243 MW of 2 filed
- Collins: 3 active, 1,140 MW of 8 filed
- Katydid Road: 4 active, 185.1 MW of 5 filed
- Dresden: 4 active, 175 MW of 6 filed
- Morris: 2 active, 32.6 MW of 3 filed
- Kendall: none active of 4 filed
- LaSalle-Braidwood: none active of 2 filed
Site Scanner