Dresden substation interconnection queue

4 active projects totaling 175 MW in the PJM queue, plus 2 with terminal status (shown grayed).

6 PJM queue filings name Dresden as the point of interconnection, all in Grundy County, IL.

Target commercial operation dates as filed run from Jan 2012 to Nov 2028 (6 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: ComEd (1 filing).

4active projects
175active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH2-421 Dresden 138kV 138 230 Battery Withdrawn Dec 2025
Q49 Dresden Nuclear Generating Station U2 345 70 Nuclear In Service Jan 2012
Q50 Dresden Nuclear Station Unit 3 345 70 Nuclear In Service Jan 2012
C01-1053 Dresden 345 kV 345 32 Nuclear Active Nov 2028
X3-045 Dresden n/r 32 Nuclear Withdrawn Jun 2014
X1-045 Dresden Nuclear Generation Station, Units 2 & 3 n/r 3 Nuclear In Service Dec 2012

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Dresden (COMED, 6 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Grundy County, IL

All 44 PJM queue filings in Grundy County, IL.